Today we were in Brussels attending ALARM Final Review Meeting and Maturity Gate. The main goals of this meeting were to present and review the project results, to assess the achievement of the project objectives and impact, and to assess the maturity achieved by the project solutions in accordance with SESAR Programme Management Handbook.

Agenda

10:00-10:10  Welcome by Project Officer & Project CoordinatorSJU+ Project Coordinator
10:10-10.55– Review of actions
– Project Goals and Objectives
– Project Solutions and target maturity levels
– WBS summary
– Progress vs Schedule and follow-up activities
– Review of Risks and Issues
– SJU Feedback on Final Project Results Report
Manuel Soler (PC)
10.55-11.25WP7: Communication, Dissemination, Exploitation, and data managementManuel Soler
11.25-11.45Coffee break 
11.45-12.05Key Achievements W2 – Alert system hosting platform.Hugues Brenot
12.05–12.25Key Achievements W3 – Dispersion modelsTim Winters
12.25-12.45Key Achievements W4 – Severe weather hazardsRicardo Biondi
12.45-13.05Key Achievements W5 – Environmental Hotspots:Simone Dietmüller
13.05-13.25Key Achievements W6 – MET Information and Alerts for ATMTanja Bolic
13.25-14.45Lunch
14.45-15.30Candidate for SESAR Solution: Self-Assessment of ALARM-Sol, Contribution to the ATM Master Plan, Follow-up R&D and Exploitation activitiesManuel Soler
15.30 – 17:00Final Project Assessment: Achievement of Project Objectives, Achieved Project Impact, Conclusions and lessons learnt at project level, Recap of Maturity Gate actionsAll